J.M.W. Turner's "Chichester Canal" at the Tate Gallery, London

Wednesday, September 14, 2016

Reopening of Route 28 bridge in Shandaken pushed back to mid-November




An unexpected problem amid the replacement of a Route 28 bridge over the Esopus Creek in the town of Shandaken have moved the anticipated reopening of the span from Oct. 7 to sometime in mid-November, according to the town supervisor.

Rob Stanley said he was told of the new target date for completion by the state Department of Transportation.

The project began in April. So far, two of three new concrete abutments have been positioned, and steel has been laid over the top of them. But construction of the third abutment, on the west side of the creek, has been held up, Stanley said.

When excavators dug down, it was discovered a shelf of bedrock on which the abutment was to sit on wasn’t exactly where expected.

It was only a few feet away, but that meant that the abutment, under the original plan, would be sitting on soft ground instead of solid rock unless changes were made. So design engineers were called in to rethink the plan and devise a new one that takes into account the real location of the rock shelf.

The result was a delay of several weeks.

When completed, the new bridge on Route 28, near the intersection with Route 42, will be longer, wider and higher than the old one and will eliminate a rail crossing where development of a recreational trail is planned.

The old bridge was 233 feet long and 33 feet wide. The new span will be 293 feet long and 40 feet wide, and the road will be 8 feet higher above the creek than the old bridge.

The anticipated traffic volume is 2,600 vehicles per day.


The posted detour for Route 28 drivers includes Route 42, Creekside Drive and Firehouse Road.

No comments:

Post a Comment